1,100-metre-long sewer rising main under an estuary

Renovation of the main in one shot

Line type

Sewer rising main

Application area

Utility

Medium

Water

Region

Nelson

Country

New Zealand

Situation

In order to meet increases in capacity requirements and to provide alternative pipe routes with the goals of establishing pipeline redundancy, improved system resilience and future proofing in line with the overall network management strategy, the operator proposed to rehabilitate the pipe crossing under an estuary and to bring it back into service. The over 1,100-metre-long pipe had been abandoned since 2007.

Special features

Pipeline's location

The pipeline is laid in the Waimea inlet on New Zealand’s South Island, which is a large and shallow tidal lagoon that has high human use and high ecological values. It is a nursery area for marine and freshwater fish, has large shellfish beds, and is very important for birdlife.

Creative solution to insert the Primus Liner in one shot

Since there was no winch with a sufficient cable length available, a trailer winch equipped with 1,000 metres of cable and another 200-metre extension was used.

Bends and installation length

The presence of bends and the sheer length of the pipeline ruled out sliplining with HDPE and also reduced close-fit HDPE.

Technical details

Material of host pipe

Asbestos cement, class B

Diameter of host pipe

DN 525

Transported fluid

Residential wastewater

Operating pressure

6 bar

Total length

1,100 m

Number of sections

1 section

Number of bends

Several

Why Primus Line?

Ability to negotiate the existing bends

Long installation length

Almost no reduction of diameter due to wall thickness of only 6 mm

Small access pits

Your product watchlist